Lusaka's main road rebuild — 67 kilometres of rehabilitation and expansion running from Airport Roundabout to Munali Roundabout — is set to be finished by 15 December 2026, the Lusaka City Council has said.
The council's Director of Engineering Services, Victor Chawinga, told ZNBC the project is worth K409 million. It began as a 41.1-kilometre job and has since grown to cover selected residential roads as well, along with dedicated bus lanes and improved access routes, he said.
Some stretches are already done. The 5.4-kilometre Ibex Road has been completed at a cost of K67 million, according to Mr Chawinga, while work on the 2.2-kilometre Chongwe Road has reached 60 per cent.
Lusaka Province Permanent Secretary Abigail Salukoma toured the ongoing works, and ZNBC reports that several key roads are being upgraded as part of the effort, including Lusaka Road, Airport Road and Tokyo Road, alongside a 21.5-kilometre Lusaka-Nakonde project.
The works are meant to ease the traffic jams that choke the city and to make it easier to move around Lusaka, ZNBC reported. UPND Media Director Mark Simuuwe, who inspected the road works, said better roads would stimulate economic activity by helping people and goods move more freely.
For drivers, the test now is the December deadline. The project has already grown well beyond its original size, and the next month will show whether the council can hold the 15 December finish it has promised.